Ridiculous: Judge Orders Construction Trump's White House Ballroom to Be Halted
Why Eric Swalwell Sent a Cease and Desist Letter to the FBI
DeSantis Demands Radical Judge's Impeachment After She Freed Predator Who Killed a Five-Ye...
Florida Attorney General Takes Bold Stance on Gun Rights Despite Criticism From Prosecutor...
Justice Jackson's Latest Dissent Reminds Us She Remains Unfit for the Supreme Court
You'll Never Guess What California Is About to Waste Billions on Now
Gavin Newsom's Press Office Trips Over His Own Ego As He Attacks Trump's...
Sherrod Brown Attends Fundraiser Hosted by Disgraced Politicians, a Felon, and a Racist
The Los Angeles Times Is Now Interested in Covering the CCP-Linked Biolab Story...
Guess Which Demographic Group Is Throwing Support Behind the Reform UK Party
Will the Insane Shutdown Ever End?
Man Charged With Robbing Teen Out of Jail After Gun Possession Arrest at...
Dan Bongino Tears Into Daily Mail Headline For Sowing Confusion Over Who Killed...
The Strait of Hormuz or the Gays of Hormuz—Watch This Actual Conversation With...
Nancy Pelosi Claims GOP Could Steal 2026 Midterms As Democrats Say Elections Are...
Tipsheet

D.C. School Renovations Run $107 Million Over Budget

D.C. School Renovations Run $107 Million Over Budget

Renovations at the Duke Ellington School of the Arts were initially estimated at $71 million, but over a period of three years, that price grew to more than $178 million. A new report by the D.C. Auditor's Office shows that the Department of General Services (DGS) made significant errors in planning the renovations, such as missing deadlines, underestimating costs, and failing to consider cheaper locations.

Advertisement

The DGS based its initial estimate on a renovation project of a traditional high school with a smaller student body than Duke Ellington's. The project assumed a population of 500 students and a square footage of 167,500, while Duke Ellington has a student population of 600 and a square footage 278,524. In addition, Duke Ellington requires additional elements for its performing arts focus, including “sound-insulated rooms, a dance studio, make-up and dressing rooms, a costume room, a scene construction shop, and a box office for ticket sales,” according to the report. The difference in size, combined with the difference of performance facilities, rendered the initial estimation inaccurate.

Another source of expense came from the decision to renovate the school in its current location rather than move it to a cheaper location nearby, such as the Ellington Field. After pushback from students and alumni, Mayor Vincent Gray of D.C. and other elected officials communicated that Duke Ellington would remain where it was. The D.C. audit report contends that these officials were not sufficiently transparent in presenting the costs and benefits of moving the location to the public, stating that not only was there “no evidence of public deliberation on location,” but also that “no cost comparison was undertaken at the time.”

Building a new school would have also allowed designers to construct the building with the arts in mind, without having to retrofit a building not designed for that purpose. Board members noted that “the current facility was never intended to serve as a school for the arts” and that a new structure would provide “a once in a lifetime opportunity to ‘get the design right’ for Ellington in a holistic fashion." The total cost for building a new school on Ellington Field would have been $105.7 million—significantly less than the cost of renovating the existing building.

Advertisement

Related:

BUDGET SCHOOLS

In addition to being over budget, the renovations have also experienced substantial delays. The DGS missed several deadlines in approving building plans and selecting architects, causing the project to begin years later than had been scheduled. While the project was scheduled to start on June 15, 2013, actual construction did not begin until April 2015.

The director for the DGS denies wrongdoing in the renovation process but asserts that the department has nonetheless implemented “various improvements…to enhance planning, accountability, and cost controls.” Construction is currently underway at Duke Ellington, though the time of the project’s completion is unknown.